Begamganj–Gairatganj Multi Village Rural Water Supply Scheme
Completed Project · Water Supply
Begamganj–Gairatganj Multi Village Rural Water Supply Scheme
A turnkey EPC project bringing 15.10 MLD of treated water from the Semari Dam to 81 villages and 2 towns in Raisen district, Madhya Pradesh, with 10 years of operation and maintenance.
CompletedEPC Turnkey · 10-Year O&MRaisen, M.P.
Begamganj-Gairatganj MVRWSS, Raisen
Project Overview
Treated drinking water for 81 villages and 2 towns
The Begamganj–Gairatganj Multi Village Rural Water Supply Scheme serves 81 villages and the towns of Begamganj and Gairatganj in Raisen district, Madhya Pradesh. Madhya Pradesh Jal Nigam Maryadit (MPJNM) awarded Jayvarudi Infracon the complete scheme as a single-package turnkey contract.
Our work covered engineering, procurement, construction, testing, commissioning and trial run of every component of the scheme. These included the intake well and approach bridge at the Semari Dam, the water treatment plant, the master balancing reservoir and the pipeline network. With 23 hours of pumping a day, the scheme has an ultimate capacity of 15.10 million litres of treated water per day.
Work began in August 2018 and was completed in July 2023. Several site issues extended the timeline: forest land permission for the master balancing reservoir, a change in the location of the water treatment plant, a location dispute at the intake well and approach bridge, and WRD land issues for blasting. Each was resolved before the scheme was commissioned. We now run and maintain the entire scheme under a 10-year operation and maintenance contract.
Contract Details
Project Information
Name of WorkEPC, testing, commissioning, trial run and O&M of various components of Begamganj-Gairatganj Multi Village Rural Water Supply Scheme, District Raisen, for 15.10 MLD treated water (23 hours of pumping) from the Semari Dam to 81 villages and 2 towns of Begamganj and Gairatganj Blocks, on turnkey basis including running and maintenance for 10 years
LocationBegamganj & Gairatganj Blocks, District Raisen, Madhya Pradesh
Agreement No.30/2018-19, dated 30 August 2018
Work Order No.4608/185/Proc./MPJNM/2018, dated 7 September 2018
Capacity15.10 MLD treated water, 23 hours pumping
Coverage81 villages and 2 towns
Tendered Amount₹84,87,00,000
Cost on Completion₹87,13,69,003
Completion Period24 months as per tender (60 months including time extension)
Year of Completion2023–24
From the Site
From Semari Dam to Every Village
Water is drawn from the Semari Dam through an intake well, treated at the water treatment plant, and then pumped through a master balancing reservoir into the pipeline network that reaches 81 villages and 2 towns.
We built and commissioned every part of this system on a turnkey basis, and our team continues to operate and maintain it so that each village and town receives a reliable supply of treated water.
Project Timeline
From agreement to commissioning
Work Started1 Aug 2018
Mobilisation & survey
Execution60 Months
Construction, testing & trial run
Completed11 July 2023
Commissioned; 10-year O&M in progress
Planning a Water Supply or Infrastructure Project?
Jayvarudi Infracon delivers complete water supply, drainage and civil infrastructure projects on time. Let's talk about your next project.