Design and construction of an underground sewerage scheme for Ratlam city in Madhya Pradesh under the AMRUT mission, executed for Ratlam Municipal Corporation.
CompletedDesign & Build · AMRUTRatlam, M.P.
Ratlam Underground Sewerage Scheme
Project Overview
A cleaner, healthier Ratlam
Ratlam Municipal Corporation set out to give the city a modern underground sewerage system under AMRUT (Atal Mission for Rejuvenation and Urban Transformation). The corporation awarded Jayvarudi Infracon the contract to design and construct the scheme.
Our work covered the design and construction of the underground sewerage network and the sewage treatment plant (STP). The network collects wastewater from the city and carries it to the STP for treatment, so it no longer flows through open drains.
Work began in December 2016 and was completed in September 2023. The timeline was extended because the Municipal Corporation paused the work for a period, the land for the STP was handed over late, and some approvals took longer than expected. The scheme was completed and commissioned after these issues were resolved, and its operation and maintenance is now in progress.
Contract Details
Project Information
Name of WorkDesign and Construction of Ratlam Underground Sewerage Scheme, District Ratlam, under AMRUT
ClientExecutive Engineer, Ratlam Municipal Corporation, Ratlam, Madhya Pradesh
LocationRatlam, Madhya Pradesh
Agreement No.B-2T/202 of 2017–18
Work Order No.90/10/Lo. Ni. Vi./16, dated 28 December 2016
MissionAMRUT (Atal Mission for Rejuvenation and Urban Transformation)
Tendered Amount₹1,23,85,85,555
Cost on Completion₹1,37,65,55,402
Completion Period36 months as per tender (completed September 2023)
Year of Completion2023–24
From the Site
Underground Sewerage Network
The scheme collects wastewater from across Ratlam through a network of underground sewer lines and carries it to the sewage treatment plant, where it is treated before disposal.
By replacing open drains with a closed underground system, the project improves sanitation and public health and gives Ratlam infrastructure ready for its future growth.
Project Timeline
From work order to commissioning
Work Started28 Dec 2016
Work order issued & mobilisation
Execution2016–2023
Sewer network & STP construction
Completed20 Sep 2023
Commissioned; O&M in progress