Pumping mains from the Dharoi intake, a 32 MLD water treatment plant and a 10 MLD underground storage reservoir at Bavalkanthiya, supplying treated water to 119 villages and 88 villages of Khedbrahma Stage 2 in Gujarat, with 5 years of operation and maintenance.
Carrying Dharoi water to the villages of Khedbrahma
This project strengthens the regional water supply for villages around Khedbrahma in Sabarkantha district, Gujarat. The P.H. Works Division of GWSSB in Himmatnagar awarded Jayvarudi Infracon the contract to build the main transmission and treatment infrastructure of the scheme.
We laid an 813 mm diameter MS pumping main from the Dharoi intake to the Dharol Campa head works, followed by a 600 mm diameter DI-K9 pumping main from Dharol Campa to Bavalkanthiya. At the Bavalkanthiya head works, we built a 32 MLD water treatment plant and a 10 MLD underground storage reservoir, along with all the electro-mechanical components. Together, these supply treated water to 119 villages and to 88 villages of Khedbrahma Stage 2.
Work began in March 2022 and was completed in July 2024. A time extension of 9 months was granted because the land for the water treatment plant was received late. The contract includes five years of operation and maintenance, which is now in progress.
Contract Details
Project Information
Name of WorkProviding and laying 813 mm dia. MS pumping main from Dharoi intake to Dharol Campa head works and 600 mm dia. DI-K9 pumping main from Dharol Campa head works to Bavalkanthiya WTP; construction of 32 MLD WTP at Bavalkanthiya head works with 10 MLD UGSR along with electro-mechanical components, covering 119 villages and 88 villages of Khedbrahma Stage 2 RWSS, including 5 years O&M
ClientExecutive Engineer, P.H. Works Division, Himmatnagar, Gujarat
LocationKhedbrahma, Sabarkantha, Gujarat
Agreement No.B-1 of 2021–22, dated 28 March 2022
Work Order No.AB/Tender/Poshina.St.1/367/2022, dated 28 March 2022
Pumping Mains813 mm dia. MS (Dharoi intake to Dharol Campa) and 600 mm dia. DI-K9 (Dharol Campa to Bavalkanthiya)
Treatment & Storage32 MLD WTP and 10 MLD UGSR at Bavalkanthiya
Coverage119 villages + 88 villages of Khedbrahma Stage 2
Tendered Amount₹76,88,76,055
Cost on Completion₹88,26,86,858
Completion Period18 months as per tender (27 months including time extension)
Year of Completion2024–25
From the Site
Intake to Treatment Plant
Raw water from the Dharoi intake travels through the 813 mm MS and 600 mm DI-K9 pumping mains to the Bavalkanthiya head works. There it is treated at the 32 MLD water treatment plant and stored in the 10 MLD underground storage reservoir before supply to the villages.
Our team built and commissioned this full chain, including the electro-mechanical systems, and continues to operate and maintain it under the five-year O&M contract.
Project Timeline
From agreement to commissioning
Work Started9 Mar 2022
Mobilisation & pipeline works
Execution27 Months
Pumping mains, WTP & UGSR
Completed22 July 2024
Commissioned; 5-year O&M in progress